Discussion Forum : Water Supply Engineering - Section 6 (Q.No. 37)
37.
Estimates of a water supply project depends upon the rate of water supply per capita consumption and probable population estimated at the end of the design period of
Discussion:
2 comments Page 1 of 1.
AKdon said:
3 years ago
Why not 10 to 15 years for water supply? Please explain me.
Heera said:
6 years ago
Ssewers: design period: 40 to 50 years.
Water supply system : design period: 20 to 30 years.
Sewage treatment plant: design period: 15 to 20 years.
Water supply system : design period: 20 to 30 years.
Sewage treatment plant: design period: 15 to 20 years.