37.
Estimates of a water supply project depends upon the rate of water supply per capita consumption and probable population estimated at the end of the design period of
5 to 10 years
10 to 15 years
15 to 20 years
20 to 30 years
25 years.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

AKdon said:   3 years ago
Why not 10 to 15 years for water supply? Please explain me.

Heera said:   6 years ago
Ssewers: design period: 40 to 50 years.
Water supply system : design period: 20 to 30 years.
Sewage treatment plant: design period: 15 to 20 years.