Civil Engineering - Water Supply Engineering - Discussion

Discussion Forum : Water Supply Engineering - Section 2 (Q.No. 1)
1.
While determining the yield of open wells by the pumping test
velocity of recharging water, increases with depression head
depression head resulting at critical velocity, is called critical depression head
working head is generally limited to rd of the critical depression head
maximum safe yield of an open well, is expected at critical depression head.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Subha Annadurai said:   7 years ago
The yield of the open well can be determined by,

1. Pumping test.
2. Recuperation test.
(1)

Apcivilian said:   8 years ago
All the options are right Here?
(1)