A unit hydrograph is a hydrograph of a rain storm of a specified duration resulting from a run-off of
Discussion:
13 comments Page 1 of 2.
TANMOY SAHA said:
1 decade ago
Can I get explanation for this question please ?
I think it will be 10 mm.
I think it will be 10 mm.
PIYUSH SINGH said:
1 decade ago
Answer should be 10 mm or 1 cm as Unit hydro graph produces runoff of 1 cm.
Mukesh maurya said:
9 years ago
The answer should be 1cm i.e.10mm.
Deepak said:
8 years ago
The answer should be 10 mm or 1 cm.
Biruk girma said:
8 years ago
Answer will be 10mm or 1cm.
Hamse dahir said:
8 years ago
Unit hydro graph produces runoff of 1 cm that means 10mm.
Sidharth said:
7 years ago
1 cm or 10 mm.
Bhagwana Ram said:
7 years ago
1 unit.
It may be mm or cm.
It may be mm or cm.
Deepak said:
6 years ago
If the rainfall distribution in the storms is similar with respect to time and area, the ordinate of each hydrograph will be proportional to volume of runoff. The unit hydrograph is a hydrograph with a volume of 1cm runoff resulting from a rainfall of specified duration and a real pattern.
Kumar said:
5 years ago
10mm ruoff.