Ventilating shafts are provided to a sewer line at every
Discussion:
4 comments Page 1 of 1.
Viki said:
5 years ago
We need to place a vent shaft about every 400 meters along a wastewater pipeline to ensure the network is ventilated properly. They are often placed at high points, at the beginning and end of wastewater pipelines, and may be located next to a maintenance hole. So 300 is appropriate.
Hariom said:
7 years ago
I think B is the answer.
Roy said:
7 years ago
Minimum 150, maximum 300. So the best option is c) 200 m.
Adhi said:
8 years ago
No, it's for 100 mtrs.