Discussion Forum : UPSC Civil Service Exam Questions - Section 25 (Q.No. 46)
46.
Why are weep holes provided at the back of retaining walls ?
To reduce the active earth pressure on the walls
To reduce the build - up of hydrostatic pressure
To provide better compaction
To increase the passive earth pressure
Answer: Option
Explanation:
No answer description is available. Let's discuss.