Duration along the critical path defines which of the following ?
1. Shortest duration needed
2. Shortest duration permissible
3. Longest duration needed
4. Longest duration permissible
Select the correct answer using the code given below :
1 and 2 only
1 and 4 only
2 and 3 only
3 and 4 only
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Rinchtar said:   5 years ago
Duration along the critical path defines the project duration. By proper planning it can be made as short as possible. Hence shorter duration is needed to complete the project in shortest time possible.

It is the maximum duration path hence the longest duration is permissible along the critical path in comparison to other path available from start to end.

Arun Kumar sah said:   5 years ago
As we know, there is no flow at the critical path which may cause the shortest duration and it shouldn't be allowed to complete the work after the duration of the critical path.

So, Option B is correct.

Tushar Dev said:   5 years ago
Thanks all.

Er.ESE KHAN said:   8 years ago
The correct answer is C.

Critical path defines the longest duration needed to complete the project and it also defines the shortest permissible duration before which project cannot be completed.

Hope this will be the correct answer.