32.
What does higher standard deviation imply in cost analysis ?
Higher uncertainty
Lower uncertainty
Nothing to do with uncertainty
Extra costs are likely
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Rahul verma said:   2 years ago
Option A is the correct answer.

A higher standard deviation implies higher uncertainty.