In drawing AOA networks and making time computations, the following processes are involved :
1. Activity listing
2. Work breakdown structure
3. Activity time allotment
4. Consideration of available resources for each activity
5. Activity dependencies
6. Float computations
7. Backward path computation
8. Project duration
9. Forward path computation
What is the correct sequence of the processes given above ?
1. Activity listing
2. Work breakdown structure
3. Activity time allotment
4. Consideration of available resources for each activity
5. Activity dependencies
6. Float computations
7. Backward path computation
8. Project duration
9. Forward path computation
What is the correct sequence of the processes given above ?
Discussion:
Be the first person to comment on this question !
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers