6. 

While driving a large number of piles in loose sand :

[A]. It is advantageous to follow a sequence of pile driving such that the inner piles are driven first and then proceed outwards
[B]. It is advantageous to follow a sequence of pile driving such that the piles near the periphery are driven first and inner piles are driven later
[C]. It is advantageous to follow a sequence of pile driving such that alternately inner and outer piles are driven
[D]. Driving of piles can be done in any random order

Answer: Option A

Explanation:

No answer description available for this question.

Sujatha said: (Oct 27, 2020)  
Please explain.

D Singh said: (Jul 15, 2021)  
Explain the answer.