Civil Engineering - UPSC Civil Service Exam Questions - Discussion
Discussion Forum : UPSC Civil Service Exam Questions - Section 25 (Q.No. 4)
4.
Which one of the following is the best method for locating sounding to estimate the dredged material from the harbours ?
Discussion:
3 comments Page 1 of 1.
Binu said:
6 years ago
The correct Answer is D.
Refer S K Duggal.
Refer S K Duggal.
Awomi said:
4 years ago
The correct answer is D. ) Fixed intersecting range.
Rahul verma said:
2 years ago
Option D is correct.
To know the amount of silting or scouring (dredged material) that happened at that point, we use intersecting method.