In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?
Discussion:
2 comments Page 1 of 1.
Sadashiva said:
8 years ago
PERT follows Beta distribution.
We're, CPM follows normal distribution.
We're, CPM follows normal distribution.
(1)
Rahul verma said:
2 years ago
Option C is the correct answer.
For pert, the Normal distribution is correct for the whole project, and individual activity follows the beta distribution.
For pert, the Normal distribution is correct for the whole project, and individual activity follows the beta distribution.