In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is
12 days
14 days
15 days
17 days
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Savair said:   7 years ago
Earliest time takes up a minimum of the incoming finish times. The Answer should be 12days.

Muhammad Atiq said:   7 years ago
17 days is correct. Because when all the previous four activities will complete then the next activity Q will start.