20.
The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along


Discussion:
3 comments Page 1 of 1.
Tanvir said:
6 years ago
How it is B? Kindly explain.
Assumi said:
4 years ago
The critical path is the longest path and it will have the maximum value.
Joae tribiani said:
1 year ago
Agree, B is the correct answer.