Civil Engineering - UPSC Civil Service Exam Questions - Discussion

34. 

Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration)
The correct sequence of computation would be

[A]. EET, PD, LET, TF
[B]. EET, PD, LET, AD
[C]. AD, EET, BP, PD
[D]. FP, EET, TF, PD

Answer: Option C

Explanation:

No answer description available for this question.

Post your comments here:

Name *:

Email   : (optional)

» Your comments will be displayed only after manual approval.