Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration)
The correct sequence of computation would be
EET, PD, LET, TF
EET, PD, LET, AD
AD, EET, BP, PD
FP, EET, TF, PD
Answer: Option
Explanation:
No answer description is available. Let's discuss.