Discussion Forum : UPSC Civil Service Exam Questions - Section 20 (Q.No. 40)
40.
In a project, the contractor is paid on the basis of the running bill for a month. The rate contract for concreting is Rs. 1000/m3 of concrete. The consumption of number of cement of bags of weight 50 kg is 527. The mix proportion for the concrete is 1: 1.4 : 2.75 with W/C ratio of 0.52. The approximate billing amount of the month will be
Discussion:
5 comments Page 1 of 1.
Aarif Majeed said:
5 years ago
C is the correct answer.
(3)
Vishalraj said:
5 years ago
I think C is correct.
(1)
Chhaya said:
8 years ago
Answer C is correct.
527 * 0.0347 * (1 + 1.4+2.75) * 1000/1.52 = 61958.90.
527 * 0.0347 * (1 + 1.4+2.75) * 1000/1.52 = 61958.90.
(2)
Santu naskar said:
8 years ago
527 * 0.0347 * (2 + 1.4+2.75) * 1000/1.54 = 61154.24.
(1)
Penny said:
8 years ago
According to me the Correct answer is C.
Post your comments here: