39.
The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is
Discussion:
1 comments Page 1 of 1.
Sadashiva said:
8 years ago
Po+Pp+4Tm/6.
= 4+12+4*11/6.
= 10 days.
= 4+12+4*11/6.
= 10 days.