41.
A hydro-electric reservoir can supply water continuously at a rate of 100 m3/s. The head is 75 m. The theoretical power that can be developed is
10000 mhp
100000 mhp
7500 mhp
7500 kW
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
7 comments Page 1 of 1.

Sonal sinha said:   8 years ago
How? Explain.

Sadashiva said:   8 years ago
Theoretical power= WQH.
= 10 * 100 * 75.
= 75000KW.

Vai said:   8 years ago
Theoretical power = 75000000 Watt (as calculated above).
1 HP = 746 W.
Theoretical power = 75000000/746 = 100536 HP.

Himani said:   7 years ago
How the value of w is 10?

Mahesh sinh said:   5 years ago
P=WQH/75.
= 1000*100*75/75,
=100000 mhp.

Dibakar said:   4 years ago
WHQ/0.746 = 10 * 7500/0.746 = 100536Hp.

Dibakar said:   4 years ago
@Himani.

Here w is unit wt of water, 10KN/m^3.