Civil Engineering - Surveying - Discussion

45. 

The additional lines which are measured to show the correctness of the chain surveying are called:

[A]. check clines
[B]. proof lines
[C]. tie lines
[D]. all of these.

Answer: Option D

Explanation:

No answer description available for this question.

Rohit said: (Apr 6, 2018)  
How is it possible?

Because a line can show one thing at a time.

Sam Khairnar said: (Mar 6, 2020)  
The check line is also known as proof line..it is used to check the accuracy of survey lines. and A"tie line" is that line which joins some fixed points called "stations" on the main survey lines. The purpose of a tie line is two-fold, i.e., firstly it enables checking of the accuracy of the network and secondly locating the interior details which are comparatively far away from the main survey lines.

Therefore answer is correct

Fahad said: (Oct 5, 2020)  
Thanks @Sam.

Mahendra said: (Nov 22, 2020)  
Thanks @Sam Khairnar.