Civil Engineering - Surveying - Discussion

17. 

While working on a plane table, the correct rule is :

[A]. Draw continuous lines from all instrument stations
[B]. Draw short rays sufficient to contain the points sought
[C]. Intersection should be obtained by actually drawing second rays
[D]. Take maximum number of sights as possible from each station to distant objects.

Answer: Option B

Explanation:

No answer description available for this question.