Civil Engineering - Surveying - Discussion

Discussion Forum : Surveying - Section 1 (Q.No. 9)
9.
In chain surveying tie lines are primarily provided
to check the accuracy of the survey
to take offsets for detail survey
to avoid long offsets from chain lines
to increase the number of chain lines.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
60 comments Page 3 of 6.

Arvind said:   5 years ago
Option B and C both are correct. Tie lines is used to avoid long offset and to locate interior details but we have to take offset from tie line to object to locate interior details.

Saurabh said:   5 years ago
Tie line is used to collect information about near by object.

Risab pant said:   5 years ago
The line which is used for checking the accuracy of work is Tie line.

Abhishek Nayak said:   5 years ago
Option B is correct.

Pramit Samanta said:   4 years ago
The tie line is to locate details, so B is the right answer.

Mithlesh said:   4 years ago
I think Option B is correct.

Pkota said:   4 years ago
Option B should be the correct answer.

Pramit Samanta said:   4 years ago
Right @Jamshaid Ahmed.

D Bharath said:   2 years ago
Tie lines is to mark the points.

Seemanjali said:   11 months ago
The correct answer is (C) To avoid long offsets from chain lines.

Tie lines in chain surveying are provided to help avoid long offsets from the main survey lines and to increase the accuracy of plotting details in a survey.