Civil Engineering - Surveying - Discussion

Discussion Forum : Surveying - Section 1 (Q.No. 9)
9.
In chain surveying tie lines are primarily provided
to check the accuracy of the survey
to take offsets for detail survey
to avoid long offsets from chain lines
to increase the number of chain lines.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
60 comments Page 1 of 6.

Jamshaid ahmed said:   4 years ago
Main line:line joining two main survey stations.
Tie line is used for surveying detail.
Check line is used for checking the work.
Base line :longest chain line.
(7)

Sheetal said:   4 years ago
Tie lines also called as check lines, are Used to check the accuracy of survey work.
(3)

Mansi Patel said:   4 years ago
Tie line is a line drawn to collect information of details of objects nearly.
(1)

Sukhwinder said:   5 years ago
Option B is the correct answer.
(1)

Saugat Oli said:   7 years ago
Given answer is correct.

Tie lines are run to avoid long offset whereas check line are run for better accuracy.

It's me said:   6 years ago
Tie lines are provided to locate the interior details which far away from the main survey line.

Dinesh sunar said:   6 years ago
The offset having their length more than 15m is called long offset so avoid the long offset to reduce error in chain lines.

Avtarchaudhary said:   6 years ago
Option B is the right answer.

Pooja said:   6 years ago
No, A is correct. Tie line is used to check the accuracy and detailing of work.

Sachin said:   6 years ago
B is the right option.

Tie lines are type of offset which are used for inner details of area.


Post your comments here: