It is more difficult to obtain good results while measuringhorizontal distance by stepping
Discussion:
13 comments Page 1 of 2.
Fakhar Naveed said:
3 years ago
The stepping method is more convenient and gives better results while measuring horizontal distance dow and the hill.
But here it is difficult to obtain good results up hill.
So the given answer is correct.
But here it is difficult to obtain good results up hill.
So the given answer is correct.
(6)
Haresh said:
8 years ago
Option B is right.
(1)
Sohail soomro said:
7 years ago
@Sreeraj.
But the downhill is B not A.
But the downhill is B not A.
(1)
Arpit biwal said:
7 years ago
I think the correct answer is B.
(1)
Shyam lal yadav said:
9 years ago
I think correct answer is option B.
Rbp said:
8 years ago
I think the correct answer is B.
Rupnar said:
8 years ago
I think the correct answer is B.
Sreeraj said:
8 years ago
Option A is correct. To obtain better results, chaining is done from top of hill to the toe i.e. downhill.
Samarth Garg said:
7 years ago
If stepping uphill, follower will have the difficult job of holding the tape, horizontal and with the end vertically over the previous arrow.
So, downhill stepping is preferred.
So, downhill stepping is preferred.
Saran said:
7 years ago
@Samarth.
If you are doing stepping then why it is needed to holding the tape?
So down the hill is difficult to perform.
If you are doing stepping then why it is needed to holding the tape?
So down the hill is difficult to perform.