11.
While surveying a plot of land by plane tabling, the field observations
12.
If α and β be the elevations of two objects A and B respectively, θ be the angle observed by a sextant. The correct horizontal angle is
13.
If vertical angles of inclined sights do not exceed 10° and non-verticality of the staff remains within 1°, stadia system of tacheometric observations are made on
14.
If the length of a chain line along a slope of θ° is l, the required slope correction is
15.
The sag of 50 m tape weighing 4 kg under 5 kg tension is roughly