1.
After prestressing process is completed, a loss of stress is due to
shrinkage of concrete
elastic shortening of concrete
creep of concrete
creep of steel
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
3 comments Page 1 of 1.

Manas Kumar Dolai said:   3 years ago
For post tensioning 10-15% loss & pre tensioning 18-25%.

Omid said:   5 years ago
Almost 15-20% stresses lost.

Ali EJaz said:   6 years ago
It should be option B.