Post tensioning system
was widely used in earlier days
is not economical and hence not generally used
is economical for large spans and is adopted now a days
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 4 of 5.

Srinivas said:   10 years ago
Generally used in T-beam girder bridges if any loading.

Nazish khan said:   1 decade ago
It is economical for larger span and increased tensile strength of concrete and to reduced sectional area.

Ramesh said:   1 decade ago
It is economical for long span.

Gayatri said:   1 decade ago
Yes we are use the prestress concrete for box girder in bridge.

Mani deepak grandhi said:   1 decade ago
It reduces self weight there by reducing bending moment and shear force, increase gap between moment of resistance and bending moment, the research is being carried out still on this process.

Avijit Kumar Maji said:   1 decade ago
Now a day Pre stress are not use.

Umamahesh.D said:   1 decade ago
Now a days prestressing by post tensioning method is most economical for large spans especially for bridges. Lesser the dead load more the resisting capacity.

Chithra t.m said:   1 decade ago
Post tensioning is how useful are economical?

Miss Rupali said:   1 decade ago
For post tensioning, while concreting any member ducts are provided intentionally through which the tendons are kept in tension will give to the member after hardening of concrete.

Mohit said:   1 decade ago
A method of prestressing concrete by tensioning the tendons against hardened concrete.