Civil Engineering - RCC Structures Design - Discussion

24. 

Pick up the incorrect statement from the following:

[A]. In the stem of a retaining wall, reinforcement is provided near the earth side
[B]. In the toe slab of a retaining wall, rein forcement is provided at the bottom of the slab
[C]. In the heel slab of a retaining wall, rein forcement is provided at the top of the slab
[D]. None of these.

Answer: Option D

Explanation:

No answer description available for this question.

Piyush Singh said: (Sep 3, 2015)  
In the Retaining wall Tensile stress develops at the filling side of the wall as the earth filling behind the wall tries to push the wall, so reinforcement will be the back face or filling side,

In Toe of the retaining wall soil pressure will be from the bottom of the toe thus main reinforcement will be at bottom.

In heel due to the filling above the heel tensile stress will develop on the upper side of the heel, so reinforcement will be provided on the upper side of the heel,

Saikiran said: (Jan 14, 2018)  
So answer is B and C both.

ThankYou @ Piyush.