25.
Newly constructed pavement with ordinary Portland cement attains its working strength after
Discussion:
4 comments Page 1 of 1.
ASho said:
5 years ago
Please give reference with the codes.
(1)
Zia said:
5 years ago
Pavements constructed with OPC attains working strength in 28 days.
Pavements constructed with Rapid Hardenning cement attains working strength in 7 days.
Usually RHC is used for Pavements.
Pavements constructed with Rapid Hardenning cement attains working strength in 7 days.
Usually RHC is used for Pavements.
Uddipan said:
7 years ago
28 days is the correct answer.
JiJay said:
7 years ago
The answer should be 7days for new roads.