Three points, A, B and C 500 m apart on a straight road have 500 m, 505 m and 510 m as their reduced levels. The road is said to have
Discussion:
36 comments Page 3 of 4.
Utsav said:
7 years ago
C is the correct answer.
Staff reading is increasing. Thus its downward slope.
Staff reading is increasing. Thus its downward slope.
Sanu Raja Shakya said:
1 decade ago
Completely disagree with answer, answer should be (B) a positive gradient between A and C.
Puspendu said:
7 years ago
According to me, Option C is right.
Sougoumarane said:
7 years ago
RL is given, not staff reading, so (B) is correct.
Paresh rawal said:
8 years ago
The correct answer is C.
Sabudana wada said:
8 years ago
C is correct answer.
Ramavtar said:
8 years ago
There are giving RL's not Staf reading.
So +grade in forward side.
So +grade in forward side.
Gubendhiran said:
8 years ago
@Chulbul.
When staff reading decrease the land or road has Rising Gradient.
When staff reading increase the land or road has Falling Gradient.
So in this question there is a Rising gradient so option B is correct.
When staff reading decrease the land or road has Rising Gradient.
When staff reading increase the land or road has Falling Gradient.
So in this question there is a Rising gradient so option B is correct.
Bipin Patel said:
8 years ago
Please note the RL of the road is given not staff readings.
So, the right answer is B.
So, the right answer is B.
Keshav said:
8 years ago
Chulbul is right. Answer should be C.