On concrete roads, the camber generally provided, is
1 in 20 to 1 in 24
1 in 30 to 1 in 48
1 in 36 to 1 in 48
1 in 48 to 1 in 60
1 in 60 to 1 in 72
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 4 of 5.

Trivo said:   6 years ago
The correct Answer is D.

PAWAN KUMAR said:   6 years ago
The correct answer is option D.
1 in 50 (2%) for heavy rainfall, and 1in 60 (1.7 %) for light rainfall.

Satyendra sahu said:   6 years ago
Option D is the correct answer.

Ron'S said:   5 years ago
Option D must be the Correct One.

Kaku said:   5 years ago
For Cement Concrete Road camber size 1 in 60 to 1 in 50.
(1)

Anirban Roy said:   5 years ago
It should be option C.
As 1÷48=2.08%. &.
1÷60=1.67=1.7%.
As for RCC surfacing, it should be 1.7-2%.

Anirban Roy said:   5 years ago
Answer should be D.

Sagar debnath said:   5 years ago
Yes, I also agree option D.

Sagi said:   4 years ago
The Answer is D.

Cement concrete light rain 1.7%.

Heavy rain 2%.

Shubham gour said:   4 years ago
Yes, Options D is correct. I too agree.