On concrete roads, the camber generally provided, is
1 in 20 to 1 in 24
1 in 30 to 1 in 48
1 in 36 to 1 in 48
1 in 48 to 1 in 60
1 in 60 to 1 in 72
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
43 comments Page 1 of 5.

Rohil said:   2 months ago
The Answer should be 1 in 50 to 1 in 60 for heavy and light rainfall.

Bernard Habu said:   3 years ago
How option D is correct? Please explain.
(1)

Mukesh Bandral said:   3 years ago
D is the correct answer.
(1)

Shubham gour said:   4 years ago
Yes, Options D is correct. I too agree.
(1)

Sagi said:   4 years ago
The Answer is D.

Cement concrete light rain 1.7%.

Heavy rain 2%.

Sagar debnath said:   4 years ago
Yes, I also agree option D.

Anirban Roy said:   4 years ago
Answer should be D.

Anirban Roy said:   5 years ago
It should be option C.
As 1÷48=2.08%. &.
1÷60=1.67=1.7%.
As for RCC surfacing, it should be 1.7-2%.

Kaku said:   5 years ago
For Cement Concrete Road camber size 1 in 60 to 1 in 50.
(1)

Ron'S said:   5 years ago
Option D must be the Correct One.