6.
On concrete roads, the camber generally provided, is
Discussion:
43 comments Page 2 of 5.
M.suna said:
8 years ago
Actually, the range of providing camber is 1 in 50 to 1 in 60 depending upon the rainfall area.
Yogesh Rajput said:
8 years ago
I think the Correct answer is D.
Ajay Kaundal said:
8 years ago
I think the correct answer is D.
Priyanka Rajput said:
8 years ago
Yeah, I agree with the answer D.
Patoliya chandresh said:
8 years ago
It should be option D.
Akshay said:
8 years ago
Yeah, I agree with the answer D.
Angshuman Betal said:
8 years ago
E option is the correct because In practice generally, we adopted camber 1 in 60 to 1 in 72 for c.c road.
Nani said:
8 years ago
D is the answer. I also agree.
Tanu said:
8 years ago
D is the right answer.
Emmy said:
8 years ago
Concrete road 1in 50 (heavy rainfall) &1 in 60 (light rainfall).