Concrete pavement is provided if daily traffic per lane exceeds
Discussion:
3 comments Page 1 of 1.
Pramit Samanta said:
5 years ago
Upto 200 ton/day Village road.
Upto 500 ton/day WBM.
Upto 1500 ton/day Bitumen macadam.
Upto 2000 ton/day Concrete pavement.
Upto 500 ton/day WBM.
Upto 1500 ton/day Bitumen macadam.
Upto 2000 ton/day Concrete pavement.
(6)
Debanjan Ganguly said:
5 years ago
If the daily traffic is more than 2000 ton/day then Concrete pavement provided.
Anna said:
5 years ago
Max daily capacity of bituminous road is 1500 tonnes/day.