If duty (D) is 1428 hectares/cumec and base period (B) is 120 days for an irrigated crop, then delta (Δ) in meters is given by
102.8
0.73
1.38
0.01
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Sheela said:   8 years ago
Thanks @Sadananda.

Sadananda said:   1 decade ago
Relationship between duty, delta & base period is:

Δ = (8.64*B)/D.

Therefore, Δ =(8.64*120)/1428.

= 0.73 meters.