Discussion Forum : GATE Exam Questions - Section 2 (Q.No. 21)
21.
If duty (D) is 1428 hectares/cumec and base period (B) is 120 days for an irrigated crop, then delta (Δ) in meters is given by
Discussion:
2 comments Page 1 of 1.
Sheela said:
8 years ago
Thanks @Sadananda.
Sadananda said:
1 decade ago
Relationship between duty, delta & base period is:
Δ = (8.64*B)/D.
Therefore, Δ =(8.64*120)/1428.
= 0.73 meters.
Δ = (8.64*B)/D.
Therefore, Δ =(8.64*120)/1428.
= 0.73 meters.
(1)