18.
Water distribution systems are sized to meet the
maximum hourly demand
average hourly demand
maximum daily demand and fire demand
average daily demand and fire demand.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Kundan said:   4 years ago
Why not option A? Explain please.

Swapnil Basu said:   4 years ago
The Distribution System should be designed for the maximum hourly draft of maximum day or coincident (Maximum daily draft) with fire, whichever is more.