Civil Engineering - GATE Exam Questions - Discussion

Discussion Forum : GATE Exam Questions - Section 5 (Q.No. 8)
8.
Mud pumping is commonly associated with
bituminous penetration mecadam construction
cement concrete pavement on granular subgrade
premixed bituminous construction
cement concrete pavement on clay sub-grade
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 1 of 2.

Phani said:   3 years ago
The water infiltrates through the joints, cracks and edges of the cement concrete pavement and get mixed with the clay below the cement concrete slab and forms the soil slurry known as mud.

Sumit said:   6 years ago
Yes, I too agree. D is the correct answer.

Sanakr said:   4 years ago
Yes, D is the correct answer.

Roy said:   8 years ago
D is the correct answer.

Roy said:   8 years ago
D is the correct answer.

Rakesh said:   3 years ago
D is the correct answer.

Dheeraj vishwakarma said:   1 year ago
D is the correct answer.

Gayathri said:   6 years ago
D is the right answer.
(1)

Mk PIPLODA said:   5 years ago
D is the right answer.

Laltu said:   3 years ago
D is the right answer.


Post your comments here: