Sand drains are used to :
reduce the settlement
accelerate the consolidation
increase the permeability
transfer the load
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
13 comments Page 2 of 2.

Ayan said:   5 years ago
Sand drain used to rate of consolidation but reduction in time required for primary settlement.

Sahil Chavda said:   5 years ago
Sand drains are used for pre-consolidation of soil pre-consolidation is one of the ground improvement technique. The sand drains to accelerate the consolidation by reducing the drainage path.

The correct answer is B.
(1)

Rahul kumar said:   4 years ago
Yes, Option B is right.