Discussion Forum : GATE Exam Questions - Section 7 (Q.No. 15)
15.
Sand drains are used to :
Discussion:
13 comments Page 1 of 2.
Rahul kumar said:
2 years ago
Yes, Option B is right.
Sahil Chavda said:
3 years ago
Sand drains are used for pre-consolidation of soil pre-consolidation is one of the ground improvement technique. The sand drains to accelerate the consolidation by reducing the drainage path.
The correct answer is B.
The correct answer is B.
Ayan said:
3 years ago
Sand drain used to rate of consolidation but reduction in time required for primary settlement.
Samir jadhao said:
4 years ago
Yes, the answer is B.
Trident said:
4 years ago
Sam@ it increases the differential settlement!
Gaurav Thosare said:
4 years ago
The correct answer is B.
Robiul Islam said:
4 years ago
I think the correct answer is B.
Sam said:
5 years ago
No sand drain is provided to reduce differential settlement so given answer Is correct.
Bhavnesh said:
5 years ago
Yes, B is correct. I agree.
Roy said:
6 years ago
B is the correct answer.