Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 24)
24.
The item of the brick structure measured in sq.m, is
Discussion:
26 comments Page 3 of 3.
Lekhnath said:
5 years ago
I think brick edging is the correct answer because it ask for brick structure and broken glass couping can be done in any structure.
Mithun said:
4 years ago
Option C is the correct answer.
(1)
Rajendra said:
4 years ago
Why not option C? Explain please.
(2)
MARCOSARS said:
4 years ago
@Mithun @ Rajendra.
Brick edging is measured in meter, or running meter, which means in terms of length, whereas in this question it has been asked for sq.m.
Brick edging is measured in meter, or running meter, which means in terms of length, whereas in this question it has been asked for sq.m.
Pinku said:
4 years ago
Explain it please.
(1)
Saugat said:
1 week ago
Broken glass coping: Measured in square meters (sq.m).
Reinforced brick work: Measured by volume (cubic meters) to account for the added reinforcement.
Brick edging: Measured in running meters (linear meters) because it is a linear feature, like a border.
Brick work in arches: Measured by volume (cubic meters).
Reinforced brick work: Measured by volume (cubic meters) to account for the added reinforcement.
Brick edging: Measured in running meters (linear meters) because it is a linear feature, like a border.
Brick work in arches: Measured by volume (cubic meters).
Post your comments here: