If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

[A]. Mid-section formula
[B]. Trapezoidal formula
[C]. Prismoidal formula
[D]. All the above.

Answer: Option D

Explanation:

No answer description available for this question.