Civil Engineering - Estimating and Costing - Discussion

Discussion Forum : Estimating and Costing - Section 1 (Q.No. 19)
19.
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
1.5 m3
2.5 m3
3.5 m3
5.0 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
24 comments Page 2 of 3.

Abhisek roy said:   9 years ago
How to calculate it? please explain.

Sundar said:   8 years ago
Anyone please explain it clearly.

MALAY DEY said:   8 years ago
How it is calculated? Please explain in detail.
(1)

Pandiyarajan said:   8 years ago
Please give the answer & explain it.

The expected out turn of cement concrete 1 : 1.5 : 3 per mason per day is?

Nadee said:   8 years ago
1 : 2 : 4 concrete, 1m3 need Labour constant.

Mixing concrete --------> 3.00 hour/m3.
Lifting and carrying concrete --------> 1.20 hour/m3.
c.compacting concrete --------> 0.80 hour/m3.
d.leveling surface of concrete --------> 0.10 hour/m3.
Total=(3+1.2+0.8+0.1) = 5.

H.J said:   8 years ago
1 : 1.5 : 3 material and grade is different. But labour constant is same. So, the answer 5.
(3)

King said:   8 years ago
1:2:4 it means M15 grade it means work in foundation which 5m^3 per mason per day.

Naven said:   7 years ago
100 M3 for 13 masons.

Per one mason =100/13=7.69m3 dry concrete,
Dry concrete= 1.52*wet concrete,
So wet = 7.69/1.52= 5 m3.
(3)

Sunnyod said:   6 years ago
Explain it.

Arun Prasad said:   6 years ago
For 10 m3 of cement concrete work.

Masons needed are 2.
Hence there is one mason, then the quantity in m3 is 5m3.