Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 19)
19.
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
Discussion:
24 comments Page 1 of 3.
Muzammil zohair said:
2 years ago
Pcc or cement concrete 1 : 2 : 4 = 5m^3/day/person.
Arul said:
2 years ago
For 1 cum how many bag of cement?
if 1:2:4 ratio
1 cum =6 bags
that means
5 cum= 30 bags
Can do this work with mason perday? Anyone, please explain me.
if 1:2:4 ratio
1 cum =6 bags
that means
5 cum= 30 bags
Can do this work with mason perday? Anyone, please explain me.
(2)
Mun chakrabortty said:
5 years ago
1:2:4 rcc work = 3.25 m3,
Cement concrete = 5m3 per mason.
Here, asked about " cement concrete" so answer 5 m3 per mason.
Cement concrete = 5m3 per mason.
Here, asked about " cement concrete" so answer 5 m3 per mason.
(1)
Shubham verma said:
6 years ago
That is cement concrete so the answer is 5 m^3.
If they use reinforced cement concrete so the answer will be 3 m^3.
If they use reinforced cement concrete so the answer will be 3 m^3.
Arun Prasad said:
6 years ago
For 10 m3 of cement concrete work.
Masons needed are 2.
Hence there is one mason, then the quantity in m3 is 5m3.
Masons needed are 2.
Hence there is one mason, then the quantity in m3 is 5m3.
Sunnyod said:
6 years ago
Explain it.
Naven said:
7 years ago
100 M3 for 13 masons.
Per one mason =100/13=7.69m3 dry concrete,
Dry concrete= 1.52*wet concrete,
So wet = 7.69/1.52= 5 m3.
Per one mason =100/13=7.69m3 dry concrete,
Dry concrete= 1.52*wet concrete,
So wet = 7.69/1.52= 5 m3.
(3)
King said:
8 years ago
1:2:4 it means M15 grade it means work in foundation which 5m^3 per mason per day.
H.J said:
8 years ago
1 : 1.5 : 3 material and grade is different. But labour constant is same. So, the answer 5.
(3)
Nadee said:
8 years ago
1 : 2 : 4 concrete, 1m3 need Labour constant.
Mixing concrete --------> 3.00 hour/m3.
Lifting and carrying concrete --------> 1.20 hour/m3.
c.compacting concrete --------> 0.80 hour/m3.
d.leveling surface of concrete --------> 0.10 hour/m3.
Total=(3+1.2+0.8+0.1) = 5.
Mixing concrete --------> 3.00 hour/m3.
Lifting and carrying concrete --------> 1.20 hour/m3.
c.compacting concrete --------> 0.80 hour/m3.
d.leveling surface of concrete --------> 0.10 hour/m3.
Total=(3+1.2+0.8+0.1) = 5.
Post your comments here: