While estimating a reinforced cement structure, the omitted cover of concrete is assumed
at the end of reminforcing bar, not less than 25 mm or twice the diameter of the bar
in thin slabs, 12 mm minimum or diameter of the bar whichever is more
for reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
5 comments Page 1 of 1.

Archana said:   8 years ago
Please tell me where to find these type of information? Is there any code available?

Ravindra Singh said:   1 year ago
In any case, as per SP: 34:1987, the cover shouldn't exceed 75 mm.

Rvsingh said:   1 year ago
Omitted cover means a cover that is left. Am I right?