45. 

Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

[A]. To have a check on a definitive cost estimate.
[B]. To check qoutations from contractors and/or sub contractors.
[C]. To compute target estimate for the owner while drawings and specifications are in initial stage.
[D]. All of these.

Answer: Option D

Explanation:

No answer description available for this question.