If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
3 comments Page 1 of 1.

Mervin said:   3 years ago
average= a+4m+b = 6/6.