21.
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Discussion:
3 comments Page 1 of 1.
Mervin said:
3 years ago
average= a+4m+b = 6/6.
Ahsan said:
4 years ago
How? Explain please.
Shivakumar said:
6 years ago
Please explain the answer.