Discussion :: Construction Management - Section 1 (Q.No.3)

3. 

The technique for establishing and maintaining priorities among the various jobs of a project, is known

[A]. Event flow scheduling technique
[B]. Critical ratio scheduling
[C]. Slotting technique for scheduling
[D]. Short interval scheduling.

Answer: Option B

Explanation:

No answer description available for this question.

Sudarshan said: (Jul 23, 2019)  
It's called critical path schedule.

Dipu Bunku Rose said: (Mar 8, 2020)  
@Sudarshan is right.

Sakshi said: (Sep 29, 2020)  
Why the critical path schedule? Explain.

Jayson R. said: (Sep 14, 2021)  
Critical in the sense that activities under this path are the priorities and cannot be delayed. The delay of any of the activities in this path is directly delay the whole project.