15.
Sand requiring a high water cement ratio, belongs to
Zone I
Zone II
Zone III
Zone IV.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
31 comments Page 2 of 4.

Sudheer rawat said:   6 years ago
Answer must be D because finer sand has more surface area to coarse sand. And more surface area needs more water to lubricate. So the correct answer is D.
(1)

Ram said:   3 years ago
Zone 4 is required more w/c ratio. Beacuse zone 4 is more finer than zone 1. And fine sand more surface area and more surface are more required w/c.
(11)

Bapan Sardar said:   6 years ago
Answer. Should be zone 4. Because zone 4 is finer than other zone so, It's surface area is more. And More surface area required More w/c ratio.

Ramniwas said:   8 years ago
In this questions the correct answer in the D.

Surface area is more then w/c is the more and zone 4 not used for engineering works.

Niranjan said:   9 years ago
Zone 4 sand is more fine. And more fine sand has more surface area. It requires more water. So the answer is zone 4.

Vijay reddy m patil said:   3 years ago
Zone 4 requires high water cement ratio because in fine sand fineness increases, surface area also increases.
(3)

Vijay said:   7 years ago
I think Zone 4 because fine sand having large surface area so w/c ratio will more require to lubricant.

Hemraj Basnet said:   6 years ago
Zone iv have more void than zone I. so more void requires more cement and water so answer should be D.

Sumit said:   7 years ago
In w/c, Water is In numerator so sand requiring more water will have more w/c ratio.

Sumit said:   8 years ago
I think option a) is correct, because same volume coarse sand required more water.