Discussion Forum : Concrete Technology - Section 4 (Q.No. 15)
15.
Sand requiring a high water cement ratio, belongs to
Discussion:
31 comments Page 2 of 4.
Bapan Sardar said:
6 years ago
Answer. Should be zone 4. Because zone 4 is finer than other zone so, It's surface area is more. And More surface area required More w/c ratio.
Hemraj Basnet said:
6 years ago
Zone iv have more void than zone I. so more void requires more cement and water so answer should be D.
Ghulam Nabi said:
7 years ago
Aswer should be zone 4. Zoning start from coarser to finer. So, zone 4 is the finer one. For finer sand surface area is more so more high water cement ratio.
Sumit said:
7 years ago
In w/c, Water is In numerator so sand requiring more water will have more w/c ratio.
Samrat said:
7 years ago
Yes, right @Sultan.
Vijay said:
7 years ago
I think Zone 4 because fine sand having large surface area so w/c ratio will more require to lubricant.
Shivam kumar said:
1 decade ago
Is it because of surface area?
Dinesh sharma said:
8 years ago
Correct answer zone-4, because zone - 4 more surface area compare to zone -1.
Sumit said:
8 years ago
I think option a) is correct, because same volume coarse sand required more water.
Garry said:
8 years ago
D is the correct answer.
Post your comments here: