8.
Expansion joints are provided if the length of concrete structures exceeds
Discussion:
18 comments Page 2 of 2.
Minesh Rathore said:
8 years ago
@Raj and @Ram 18-22 m take on concrete roads.
45 m takes on Rcc structures.
45 m takes on Rcc structures.
Minesh said:
8 years ago
And in wall 30m provided exp joint.
Mathan said:
7 years ago
But in practical we give extension gap for every 10m for retaining wall.
Niranjan said:
6 years ago
45m is correct according to IS:456-2000 clause no:27.2.
Majeed said:
5 years ago
Expansion and contraction joints are provided if the length of concrete structures exceeds 12 meters in length.
Reference: R Agore.
Reference: R Agore.
Gautam Dan said:
5 years ago
These joint provided in all the concrete structure of length exceed 12m.
Ref: R. K. RAJPUT.
Ref: R. K. RAJPUT.
Deepak said:
3 years ago
Right, thanks all.
Raja Biswas said:
3 years ago
Yes, it's More than 45 m.