48.
Pick up the incorrect statement from the following :
the width of the wall is constructed thicker at the base in a stepped fashion
a long vertical load transferring concrete structure is called a concrete pile
in pile which transfers the load to the soil by the friction between the pile and the surrounding soil is called friction pile.
the pile which transfers the load to a hard rock bed at certain depth is called load bearing
none of the these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

M. Waseem said:   5 months ago
How and in which condition A is correct?

Please explain me.

Apcivilian said:   5 years ago
D is also right.

Rahul said:   6 years ago
It is an end bearing so the answer is correct.

Murphy Pavendan said:   9 years ago
Load bearing pile must attain the depth of hard rock not certain depth.