The form work from the underside of slabs, can be removed only after
Discussion:
11 comments Page 2 of 2.
Sagar Bahule said:
7 years ago
It depends upon the span length of the slab as the span of the slab is,
1) Less than the 5 m =07 days of curing.
2) Exceeding 5 m=14 days of curing.
1) Less than the 5 m =07 days of curing.
2) Exceeding 5 m=14 days of curing.